Monday, November 30, 2015

November 2015 Neighbors

I asked Jeremy to move the trailer two week ago. That must have been November 14th when we caught them outside. He said he would move it for us. I showed him the stake in the ground at the telephone pole too.

He moved the trailer around Wednesday, November 25th, 2015.

He said his wife Sonya is going to hire a surveyor to figure out their land boundary.



Toby and Nikki Hughes live behind us.


Sunday, August 16, 2015

Sprint 0 through 6

We purchased a house on July 6, 2015.
We're remodeling.
I use SCRUM at work, so we're gonna start scrumming this thing.
The previous 6 sprints were just getting our bearings and our feet wet.
Today is August 16, so we're headed into in what shall be called Sprint 6.

Sprint 0 (July 6 - 11)
scraping popcorn ceiling in master bedroom
Yard cleanup
Copper head

Sprint 1 (July 12 - 18)
Yard cleanup
scraping popcorn ceiling in master bedroom

Sprint 2 (July 19 - 25)
Yard Cleanup
Cedar tree removal

Sprint 3 (July 26 - Aug 1)
master bathroom demolition
S: master bathroom shower removal

Sprint 4 (Aug 2 - 8)
M: master bathroom demolition

Attic work (1 of 3) for master bathroom

Sprint 5 (Aug 9 - 15)
M: Attic work (2 of 3) for master bathroom
T: master bathroom tile removal (partial)
W:
R: Living room panel removal
R: Cleaned windows

Sprint 6 (Aug 16 - 22)
Goal:
S: Call Habitat for Humanity
S: Call junk removal number
S: Reply to Matthew
S: Call Tile experts & Bruce
L: Kitchen-bathroom demolition
L: Kitchen demolition
M: Attic work (3 of 3) for master bathroom
M: Remove remaining paneling from living room
L: Install drywall in living room

A few notes of interest:

Our sprints are 1 week long. We review, retro, and plan on Sundays. We do daily stand-ups at totally random moments for no specific duration.

We're a 2-person scrum team. It should be 3 to 9 to work best. Maybe, between our parents and grandparents, we're a 3- or 4-man-equivalent team.

Chels and I are also the project owners. There should only be one owner, but I defer to Chelsey, so it's close enough for us.

To keep things simple for those SCRUM-averse, or not used to scrum terminology, I'm relabeling things:  We have a project goal and a sprint goal (versus 'backlogs')

We use Asana.com to plan, track, and prioritize our goals.