We purchased a house on July 6, 2015.
We're remodeling.
I use SCRUM at work, so we're gonna start scrumming this thing.
The previous 6 sprints were just getting our bearings and our feet wet.
Today is August 16, so we're headed into in what shall be called Sprint 6.
Sprint 0 (July 6 - 11)
scraping popcorn ceiling in master bedroom
Yard cleanup
Copper head
Sprint 1 (July 12 - 18)
Yard cleanup
scraping popcorn ceiling in master bedroom
Sprint 2 (July 19 - 25)
Yard Cleanup
Cedar tree removal
Sprint 3 (July 26 - Aug 1)
master bathroom demolition
S: master bathroom shower removal
Sprint 4 (Aug 2 - 8)
M: master bathroom demolition
Attic work (1 of 3) for master bathroom
Sprint 5 (Aug 9 - 15)
M: Attic work (2 of 3) for master bathroom
T: master bathroom tile removal (partial)
W:
R: Living room panel removal
R: Cleaned windows
Sprint 6 (Aug 16 - 22)
Goal:
S: Call Habitat for Humanity
S: Call junk removal number
S: Reply to Matthew
S: Call Tile experts & Bruce
L: Kitchen-bathroom demolition
L: Kitchen demolition
M: Attic work (3 of 3) for master bathroom
M: Remove remaining paneling from living room
L: Install drywall in living room
A few notes of interest:
Our sprints are 1 week long. We review, retro, and plan on Sundays. We do daily stand-ups at totally random moments for no specific duration.
We're a 2-person scrum team. It should be 3 to 9 to work best. Maybe, between our parents and grandparents, we're a 3- or 4-man-equivalent team.
Chels and I are also the project owners. There should only be one owner, but I defer to Chelsey, so it's close enough for us.
To keep things simple for those SCRUM-averse, or not used to scrum terminology, I'm relabeling things: We have a project goal and a sprint goal (versus 'backlogs')
We use Asana.com to plan, track, and prioritize our goals.